ONLY FOR OPERATIONAL PURPOSE
EXECUTIVE  SUMMARY
DPR FOR DATED :- 09 Jul 10 Page-1
DPR FOR DATED :- 09 Jul 10 FRIDAY
1 MPSEB THERMAL  GENERATION MAX. 1564 MW MIN. 1362 MW
2 MPSEB HYDEL GENERATION MAX. 327 MW MIN. 0 MW
3 INDIRA SAGAR MAX. 544 MW MIN. 0 MW
4 OMKARESHWAR MAX. 289 MW MIN. 52 MW
5 SARDAR SAROVAR MAX. 541 MW MIN. 0 MW
6 SCHEDULE FROM CENTRAL SECTOR( ISGS INCL DVC) MAX. 1737 MW MIN. 1601 MW
7 ADDITIONAL POWER PURCHASE MAX. 0 MW MIN. 0 MW
8 SALE OF POWER MAX. -333 MW MIN. -40 MW
9 EXCHANGE OF POWER MAX. 0 MW MIN. 0 MW
10 BANKING / SALE OF POWER MAX. -175 MW MIN. -403 MW
11 SCHEDULED DRAWAL (ISGS+PP+SSP+ SEZ  +DVC) MAX. 1826 MW MIN. 1241 MW
12 SALE OF POWER TO PTC MAX. #REF! MW MIN. #REF! MW
12 ACTUAL  DRAWAL(ISGS+PP+SSP+ SEZ+DVC) MAX. 2042 MW MIN. 1273 MW
13 EX(+) \ LESS(-) OVER DRAWAL  (UI) MAX. 418 MW MIN. -311 MW
AT 3 HRS AT 10 HRS
O/D FOR 16 HRS U/D FOR 8 HRS
14 OTHERS MAX. 0 MW MIN. 0 MW
15 DEMAND MET                 MAX. 4207   MIN. 2638 MW
16 FREQUENCY MAX. 50.28Hz Time  15:02 Hrs MIN. 49.11 Hz Time  21:20 Hrs
17 NO. OF TIMES WHEN UNDER FREQUENCY OPERATED :-   48.8 Hz--> 0 48.6 Hz--> 0 48.2 Hz--> 0  
18 Holiday/Special Occasion NORMAL/ CLOUDY
19 Weather Condition   Temp--> Max 0C Time Min 0C Time
29 15:25 Hrs 25 5:45 Hrs
DATE :- 10 Jul 10 SATURDAY
1 THERMAL CAPACITY AVAILABLE       2147.5 MW       2932.5
2 THERMAL UNITS OUTAGES       785 MW      
    (a) FORCED       392.5 MW ATPS # 3, SGTPS # 4 & STPS # 5
    (b) PLANNED       392.5 MW ATPS # 4 & STPS # 1, # 8
3 EXPECTED THERMAL GENERATION                 
    (MORNING / EVENING / OFF PEAK)  1450/1550/1450 MW      
4 HYDEL UNITS OUTAGES       0 MW      
    (a) FORCED       0 MW 0    
    (b) PLANNED         MW 0    
5 EXPECTED HYDEL AVAILABILITY           0    
    (MORNING / EVENING / OFF PEAK)  85/625/85  MW      
6 EXPECTED UNITS COMING UP (a)THERMAL       (b)HYDEL NIL  
                   
REMARKS -
1 VSTPS   # 3 :- UNIT TRIPPED AT 12.42 HRS./ 09.07.2010 DUE TO DRUM LEVEL LOW. AND SYNCRONISED AT 02.23 HRS / 10.07.2010.
SHIFT INCHARGE (SLDC)