ONLY FOR OPERATIONAL PURPOSE
EXECUTIVE  SUMMARY
DPR FOR DATED :- 10 Jul 10 Page-1
DPR FOR DATED :- 10 Jul 10 SATURDAY
1 MPSEB THERMAL  GENERATION MAX. 1598 MW MIN. 1425 MW
2 MPSEB HYDEL GENERATION MAX. 256 MW MIN. 0 MW
3 INDIRA SAGAR MAX. 543 MW MIN. 0 MW
4 OMKARESHWAR MAX. 291 MW MIN. 0 MW
5 SARDAR SAROVAR MAX. 541 MW MIN. 86 MW
6 SCHEDULE FROM CENTRAL SECTOR( ISGS INCL DVC) MAX. 1793 MW MIN. 1636 MW
7 ADDITIONAL POWER PURCHASE MAX. 0 MW MIN. 0 MW
8 SALE OF POWER MAX. -386 MW MIN. -120 MW
9 EXCHANGE OF POWER MAX. 188 MW MIN. -63 MW
10 BANKING / SALE OF POWER MAX. -225 MW MIN. -403 MW
11 SCHEDULED DRAWAL (ISGS+PP+SSP+ SEZ  +DVC) MAX. 1845 MW MIN. 1229 MW
12 SALE OF POWER TO PTC MAX. #REF! MW MIN. #REF! MW
12 ACTUAL  DRAWAL(ISGS+PP+SSP+ SEZ+DVC) MAX. 1782 MW MIN. 1268 MW
13 EX(+) \ LESS(-) OVER DRAWAL  (UI) MAX. 273 MW MIN. -333 MW
AT 7 HRS AT 21 HRS
O/D FOR 16 HRS U/D FOR 8 HRS
14 OTHERS MAX. 0 MW MIN. 0 MW
15 DEMAND MET                 MAX. 4006   MIN. 2665 MW
16 FREQUENCY MAX. 50.41Hz Time  15:03 Hrs MIN. 49.36 Hz Time  19:12 Hrs
17 NO. OF TIMES WHEN UNDER FREQUENCY OPERATED :-   48.8 Hz--> 0 48.6 Hz--> 0 48.2 Hz--> 0  
18 Holiday/Special Occasion NORMAL/ CLOUDY
19 Weather Condition   Temp--> Max 0C Time Min 0C Time
34 15:35 Hrs 25 6:20 Hrs
DATE :- 11 Jul 10 SUNDAY
1 THERMAL CAPACITY AVAILABLE       2147.5 MW       2932.5
2 THERMAL UNITS OUTAGES       785 MW      
    (a) FORCED       182.5 MW ATPS # 3,  & STPS # 5
    (b) PLANNED       602.5 MW ATPS # 4,  STPS # 1, # 8  & SGTPS # 4
3 EXPECTED THERMAL GENERATION                 
    (MORNING / EVENING / OFF PEAK)  1575/1550/1600 MW      
4 HYDEL UNITS OUTAGES       0 MW      
    (a) FORCED       0 MW 0    
    (b) PLANNED         MW 0    
5 EXPECTED HYDEL AVAILABILITY           0    
    (MORNING / EVENING / OFF PEAK)  85/625/85  MW      
6 EXPECTED UNITS COMING UP (a)THERMAL       (b)HYDEL NIL  
                   
REMARKS -
1
SHIFT INCHARGE (SLDC)