STATEMENT  3
DATE :- 25-Jul-10
 
AVAILABILITY PARTICULARS TOTAL ENERGY    IN LU Current Year : 2010-11 Last year : 2009-10
MORNING PEAK
MW AT 05:00 Hrs
EVENING PEAK
MW AT 22:00 Hrs
MORNING PEAK
MW AT 06:00Hrs.
EVENING PEAK
MW AT 20:00 Hrs.
   
THERMAL AVAILABILITY(2772.5 MW) 234.75 1048 1052 1308 1269
HYDEL  AVAILABILITY (915 MW) 54.53 188 396 352 423
DEEMED EXPORT TO MSEB FROM PENCH     -0.59 0 -9 -54 -52
TOTAL AVAILABILITY 288.70 1236 1439 1606 1640
Indira Sagar 26.49 0 448 122 367
OMKARESHWAR 13.74 0 155 52 52
INJECTION FROM STOA     2.30 11 18 13 13
Schedule FROM NTPC+others AFTER LOSSES(CSS+SSP+DVC+RIHAND+MATATILA) 460.48 1853 2204 1922 2212
ADDITIONAL POWER PURCHASE             1.34 190 -48 0 0
UI ENERGY (over/Under Drawal) 31.96 105 -133 -75 -220
SALE OF POWER     -13.60 -40 -120 0 0
EXCHANGE OF POWER 1.34 190 -48 0 0
ADDITIONAL POWER PURCHASE 0.00 0 0 0 0
BANKING  OF POWER -60.94 -244 -246 -185 -215
DRAWAL SCHEDULE OF STOA (WHEELING) -2.30 -11 -18 -13 -13
OTHER  IMPORT/EXPORT -1.38 0 0 0 0
Export to  (Ujjain-Kota)/ Bina (up) to Morwa 0.00 0 0 0 0
Energy Supply / Demand Met 746.79 3100 3699 3443 3836
Schedule Load Releif (MW)   671 1116 0 726 0
UnSchedule Load Shed (MW)   0.00 0.00 317 0
Frequency  (Hz)   49.94 50.10 49.58 49.36
UNRESTRICTED DEMAND (IN MW)   3780 4813 3820 4652
POWER HOUSE WISE GENERATION
INSTALLED CAPACITY            IN MW Daily GENERATION
IN  MU
Monthly Target PLF  (R-03) Plant Load Factor
YEAR : 2010-11 YEAR : 2009-10
Daily Monthly Yrly PLF % Monthly PLF% Yrly PLF%
SANJAY GANDHI 1340 5.54 72.70 17.21 50.32 61.79 61.44 68.29
SATPURA 1142.5 16.55 67.30 60.36 53.53 60.45 40.35 57.20
AMARKANTAK 450 4.85 60.60 44.91 34.12 42.15 46.11 51.14
TOTAL 2932.5 26.94 68.75 38.27 49.08 58.25 46.03 58.01
OUTAGE/MAINTENANCE            
PLANNED / FORCED OUTAGES UNIT NO. CAPACITY MW TRIPPRD SYNCHRONISE REASON EXPECTED SYN. DATE
TIME / DATE TIME / DATE
ATPS 4 120 01.05 / 21.07.09   C.O.H. 02.08.2010
SGTPS 4 210 16.00 / 07.07.10   B.PUFFING / C.O.H. 31.08.2010
SGTPS 3 210 12.31 / 16.07.10   FURNACE DISTURBANCE / AOH 02.08.2010  
SGTPS 5 500 06.58 / 21.07.10 3.25 / 26.07.10 B.T.L.    
               
             
               
               
             
TOTAL   540.00        
% OUTAGES 19.48  
 
   
COAL STOCK  FOR DATED :-25-Jul-10    
Amarkantak 82216        
Satpura 189826        
Birsingpur 116273        
STATUS AT 06.30 A.M ON DTD. :-26-Jul-10         3445
THERMAL Ex Bus 1184  MW        
HYDEL (OWN+ISP) 69  MW        
SCH(CS+PP+SSP) 1684  MW        
DRAWAL 1421  MW        
OTHER EXP/IMP (Ujj-Kota)    MW        
TOTAL 2674  MW        
Maximum Unrestrcited Demand During Night Hrs (00.00 to 06.00 hrs.) on dtd.:-25-Jul-10 4472 MW Corresponding Demand Met 3799 MW
Maximum Unrestrcited Demand During Day Time (06.00 to 18.00 hrs.) on dtd.:-25-Jul-10 3530 MW Corresponding Demand Met 2700 MW
Expected supply hours for dtd. :-26-Jul-10
Commissionary HQ 24.00 hrs    
District HQ 22.00 hrs      
Tahsil HQ 14.00 hrs    
Rural 12.00 hrs    
         
   
12.10 / 19.01.10