NATIONAL HIGHWAY ZONE, MADHYA PRADESH
ANNUAL PLAN APPROVED BY MOSRT&H FOR 2006-2007
| Sr. No | Head | NH. No. | NAME OF WORKS | LENGTH IN KMS / M. | APPROX. COST (Rs. In Crores) | REMARKS |
| A. | Expressway | Nil | ||||
| i) FS/Detailed Engineering | ||||||
| Sub Total :- | ||||||
| ii) L.A. | ||||||
| Sub Total :- | ||||||
| iii) Construction | ||||||
| Sub Total :- | ||||||
| Total | 0 | |||||
| B. | Four Lanning | |||||
| (i) FS/Detailed Engineering | 7 & 27 | FROM Km.141/6 to 229/2, Km.243/6 to 352/6 and Km.46/6 to 98/250 of NH-27 | 165 | 3.5 | ||
| Sub Total | 165 | 3.5 | ||||
| ii) L.A. | ||||||
| Sub Total :- | ||||||
| iii) Construction | ||||||
| Sub Total :- | ||||||
| Total | 165.00 | 3.50 | ||||
| C. | Bypasses | |||||
| i) FS/Detailed Engineering | 12 Ext | Khilchipur Town | 7.00 | 0.12 | ||
| 69 | Itarsi | 8.00 | 0.13 | |||
| 7 | Sihora, Panagar | 5.00 | 0.10 | |||
| 59A | Harda & Timrni | 5.00 | 0.10 | |||
| 86Ext | Sagar | 15.00 | 0.15 | |||
| ii) L.A. only | ||||||
| iii) Construction | ||||||
| Total | 40.00 | 0.60 | ||||
| D. | R.O.B./R.U.B. | |||||
| i) FS/Detailed Engineering | 86 | Km.5/10 Sagar | 1.00 | 0.10 | ||
| Sub Total :- | ||||||
| ii) L.A. | ||||||
| iii) Construction | 7 | Maihar | 5.00 | 8.00 | ||
| Total | 6.00 | 8.10 | ||||
| E. | Missing Link/New National Highways | |||||
| (i) FS/Detailed Engineerig | ||||||
| Total | 0.00 | 0.00 | ||||
| F. | Widening to two lane. | 86 | Km.44 to 50, 52, 54 to 58, 60, 61, 65, 66 to 68 | 20.00 | 3.50 | |
| 69 | Km.62 to 88 | 27.00 | 4.50 | |||
| 69 | Km.140 to 189 | 49.00 | 7.00 | |||
| 78 | Km.5 to 13, 37 to 73, 103 to 132 | 75.00 | 10.60 | |||
| 92 | 10, 11, 15 to 19, 28 to 32, 33 to 45, 79 to 88 | 25.00 | 4.00 | |||
| 59A | Km.192 to 215, 276/6 to 278, 242 to 265 | 37.00 | 5.60 | |||
| 59A | 5 to 21, 93 to 109 | 34.00 | 5.60 | |||
| 75 | 84/4 to 104, 63, 64 | 22.60 | 3.50 | |||
| Total | 289.60 | 44.30 | ||||
| G. | Widening to two lane with Geometrics Improvement. . | |||||
| Total | 0.00 | 0.00 | ||||
| H. | Strengthening | 3 | Km.410 to 416, 426 to 438 | 20.00 | 3.50 | |
| 7 | Km.473 to 484 | 12.00 | 2.50 | |||
| 69 | Km.56 to 60 | 5.00 | 1.00 | |||
| Total | 37.00 | 7.00 | ||||
| I. | Improvement of riding quality | |||||
| Total | 0.00 | 0.00 | ||||
| J. | Paved Shoulders | NHs | L.S. | |||
| Total | 0.00 | 0.00 | ||||
| K. | Widening/reconstruction of culvert | All NHs | Reconstruction of old and damaged culverts in All NHs | 2.00 | ||
| Total | 2.00 | |||||
| L. | Major Bridge | |||||
| (i) Reconstruction/ Widening | 75Ext | Nowa Nalla | 1.00 | 3.20 | ||
| 7 | 423/4 Hiran | 1.00 | 2.50 | |||
| Sub Total | 5.70 | |||||
| (ii) Rehabilitation | 12 | Sindoor (130/2, 162/4, 167/4) | 3.00 | 0.50 | ||
| 3 | Km.136/6 | 0.30 | ||||
| 3 | Km.128/2 | 0.30 | ||||
| 12 | Birang Km.119 | 0.30 | ||||
| 3 | Km.553/8 | 0.30 | ||||
| 59A | Nemawar Bridge | 0.30 | ||||
| 3 | Deb Bridge 119/4 | 0.30 | ||||
| Sub Total | 2.30 | |||||
| M | Minor Bridge | |||||
| (i) Reconstruction/ Widening | 59 | Km.6/2, 20/10, 31/4, 36/6, 61/8 | 4.00 | 0.80 | ||
| 92 | Br. In Km.42/2, 64/4 | 2.00 | 0.80 | |||
| 12Ext | km.49/6, 51/6 | 2.00 | 0.80 | |||
| 3 | Km.180/10, 217/6 | 2.00 | 0.80 | |||
| 3 | Km.350/4, 356/6, 357/4, 360/8, 362/2, 402/6 | 6.00 | 2.50 | |||
| 3 | Km.402/6, 409/8, 415/6, 436/4, 439/2, 542/4 | 6.00 | 3.50 | |||
| 27 | Km.52/8, 61/6, 63/6, 65/2, 65/8 | 5.00 | 1.50 | |||
| 86Ext | Km.39/6 to 102 | 2.00 | 1.00 | |||
| 12A | Km.46/2 | 1.00 | 0.30 | |||
| Total | 30.00 | 12.00 | ||||
| N. | Road Safty & environment | NHs | L.S. | 1.50 | ||
| (i) Crash Barrier | L.S. | |||||
| Total | 1.50 | |||||
| O. | Feasibility study/ D.P.R. for bridges | L.S. | 1.00 | |||
| Total | 1.00 | |||||
| P. | Misc. | Road safety works, way side amenities | 0.00 | 0.00 | ||
| L.A., Survey & Investigation, Bridge approach, protection works, paved shoulder with side drains | 2.00 | |||||
| Survey Investigation, repair rehabilitation minor bridge costing less than Rs.50 Lakhs | 0.00 | |||||
| Total | 2.00 | |||||
| Grand Total | 90.00 |