NATIONAL HIGHWAY ZONE 

            PUBLIC WORKS DEPARTMENT           

PHYSICAL AND FINANCIAL PROGRESS OF THE WORKS ON NHs IN M.P. (ENDING 05/2006)

S. NO. PARTICULARS IRQP (Kms.) ONGOING WORKS WIDENING / STRENGTHENING (Kms.) PERIODICAL RENEWAL (Kms.) TOTAL                             IRQP+WID&STR+PR (Kms.)
  A] PHYSICAL         
1 Total No. of Kms. in progress as on 01/04/2006 (IRQP-28 Nos., NHO-60 Nos., PR-23 Nos.) = 111 Nos. 214.00 338.00 183.00 735.00
2 Total No. of  newly sanctioned during 2006-2007 0.00 0.00 0.00 0.00
3 Total No. of Kms. in progress in 2006-2007 214.00 338.00 183.00 735.00
4 Total No. of Kms. completed During 2006-2007  (IRQP-13 Nos., NHO-4 Nos., PR-15 Nos.) = 32 Nos. 59.00 38.00 121.00 218.00
5 Balance Kms. in progress in 2006-2007 (Balance Jobs 79 Nos.) 155.00 300.00 62.00 517.00
           
  B] FINANCIAL 5054 PLAN 3054 NON PLAN TOTAL                             5054(P)+3054(NP)
1 Allocation during 2006-2007 (Rs. In crores) 80.00 58.94 138.94
2 Expenditure during 06-07 (Rs. In Crores) 15.10 8.33 23.43
  Percentage of total allotment. 18.88 14.13 16.86