| Contracts for Works: | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Name of CE | Name of Division | Contract No. | No.-Scheme | Name of Scheme |
Name of Contractor | Contract Amount Rs. In Lakhs. | Date of | Remark | ||
| Sign of Contract | Actual start of work | Completion | Executed/ to be executed | |||||||
| NT, Indore | Ujjain | 1 | 1 | Laxmipura | M/s O.P. Maheshwari | 204.99 | 01.06.06 | 01.06.06 | 30.06.08 | Contract Terminated on dated 03.05.08 and to execute balance work, tender invited on 16.07.08. |
| 2 | Pachola | - | ||||||||
| 3 | Koyalkhedi | - | ||||||||
| Ujjain | 2 | 4 | Silarkhedi | M/s Banco | 208.32 | 13.04.07 | 13.04.07 | 30.06.08/ 30.06.09 | - | |
| Shajapur | 3 | 5 | Siloda | Sitala Construction | 146.58 | 04.06.08 | 04.06.08 | 29.09.09 | The contractor has mobilized. | |
| YB, Gwalior | Morena | 4 | 6 | Rehabilitation of Ambah Branch Canal from Km 0.00 to Km. 143. 40 (Slice No. 2) |
M/s SEW | 8671.48 | 19.12.2007 (w.o.) 22.12.07 | 08.02.08 | 21.12.2010 | - |
| Sheopur | 5 | 6 | Rehabilitation of Chambal Right Main Canal from km 0 to km 60 |
M/s S.K. Jain | 14568.82 | 12.11.07 | 20.04.08 | 11.11.2010 | - | |
| Sheopur | 6 | 6 | Rehabilitation of Chambal Right Main Canal from km 60 to km 93 (Slice 1a) |
M/s Som Dutt | 5299.9 | 08.03.08 | 26.04.08 | 07.03.2011 | - | |
| Sabalgarh | 7 | 6 | Rehabilitation of Chambal Right Main Canal from km 93 to km 169 (Slice 1B) |
M/s Som Dutt | 6394.25 | 08.03.08 | 01.05.08 | 07.03.2011 | - | |
| Joura | 8 | 6 | Rehabilitation of Morena Branch Canal from km 0 to km 36.10 (Slice 4) |
M/s S.K.Jain | 2942.89 | 05.01.2008 | 15.04.2008 | 04.01.2011 | - | |
| Dabra | 9 | 7 | Restructuring of Harsi Main Canal Km. 0 to Km. 65 |
M/s SEW | 5742.49 | 22.03.06 | 22.03.06 | 21.07.06/ 31.03.08 | On Extn. 22.07.07 to 31.03.08 | |
| 10 | 7 | Restructuring of Harsi Dam |
M/s B.P. Sharma | 400.6 | 26.10.06 | 26.10.06 | 25.10.07 | Work Completed | ||
| 11 | 7 | Restructuring of Salwai Pick-up Weir |
M/s Universal Engg. | 292.17 | 02.11.06 | 02.11.06 | 02.11.07 | Work Completed | ||
| 12 | 7 | Restructuring of Distributory 9A to 14B |
M/s Banco Construction | 1064.79 | 31.07.07 | 31.07.07 | 30.11.08 | - | ||
| 13 | 7 | Restructuring of Distributory 1A to D-2 and D-3B to D8 |
Sarthi Cont., Gwalior | 833.85 | 24.12.07 | 24.12.07 | 23.06.09 | - | ||
| 14 | 7 | Restructuring of Distributory D-3A | M/s Sai Laxmi onstruction Co., AP | 1722.04 | 08.02.08 | 08.02.08 | 07.02.10 | - | ||
| 15 | 7 | Restructuring of Distributory D-15 A to D-17 |
M/s A.N.S. Construction, New Delhi | 3184.97 | 08.02.08 | 08.02.08 | 07.02.2010 | - | ||
| Dam Safety Dn.Gwalior | 16 | Water quality enhancement Swarna Rekha River |
M/s Uday Pratap Sharma,Gwalior | 3784 | 31.03.08 | 31.03.08 | 31.03.10 | - | ||
| CB, Bhopal | Bhopal | 17 | 8 | Kerwan Medium Irrigation Scheme | Bundela Constructions | 370.92 | 04.01.08 | 24.01.08 | 03.07.09 | - |
| Sanjay Sagar (P) Bah River Dn., Ganjbasoda | 18 | 9 | Kethan Medium Project (H/W & Main Canal) |
S.R. Construction, Bhopal | 282.96 | 14.03.07 | 14.03.07 | 13.03.08 (Extn. Given up to 30.06.08) Extn app. Up to 30.06.09 | - | |
| - | 19 | 9 | Kethan Medium Project (Design/Drawing/ Fixing & Testing of Automatic Tilting Gate) |
M/s Surana Fabricators | 82.77+9.58 | 14.02.07 | 14.02.07 | 13.10.07 (Extn. Given up to 31.04.08) | - | |
| Vidisha | 20 | 10 | Bardha Tank | M/s S.K.Jain | 328.55 | 16.04.08 | 17.04.08 | 17.10.09 | - | |
| Vidisha | 21 | 13 | Jajon | M/s S.K.Jain | 417.85 | - | Bid approved 14.07.08 | - | - | |
| ASHOK NAGAR | 22 | 14 | Sakarra Tank | M/s Siddharth Builders | 76.7 | 30.06.07 | 30.06.07 | 29.04.08 (Extn app. Upto 31.12.08) | - | |
| 23 | 15 16 | Koncha Mola | M/s Bundela Bandhu | 1410.24 | - | 14.08.08 | 13.08.10 | - | ||
| DK, Sagar | W.R. Dn-1 Sagar | 24 | 17 | Narayanpura | M/s Tulsiram & Co. | 234.64 | 28.05.08 | 28.05.08 | 27.11.09 | - |
| 18 | Baraitha Tank | - | - | - | - | - | ||||
| 19 | Binaika Tank | - | - | - | - | - | ||||
| 20 | Ramtoria Tank | - | - | - | -- | -- | ||||
| 21 | Bamnora Tank | - | - | - | - | - | ||||
| 22 | Dalipura Tank | - | - | - | - | - | ||||
| 23 | Kirat Sagar | - | - | - | - | -- | ||||
| 25 | 24 | Tigoda Tank | M/s Trimurti constructions | 30.39 | 23.06.08 | 23.06.08 | 22.06.09 | |||
| 26 | 25 | Paniya Tank | M/s Tulsiram & Co. | 35.3 | 28.05.08 | 28.05.08 | 27.05.09 | |||
| 26 | Ghuwara Tank | |||||||||
| Damoh | 27 | 27 | Bhat Khamariya Tank | M/s Trishul, Jabalpur | 86.56 | 27.01.07 | 27.01.07 | 26.07.07 | ||
| 28 | 28 | Majhgawan Hansraj Tank | M/s Bundela Bandhu | 208.87 | 13.09.07 | -- | 12.08.08 | |||
| 29 | 29 | Devendra Nagar | M/s S.K. Jain | 1092 | 11.11.06 | 11.11.06 | 11.11.08 | Tender Termination on date. 22.4.08 | ||
| 30 | Brijpur Tank | - | - | - | - | - | ||||
| 30 | 31 | Amkhera Tank | M/s S.K. Jain | 150.07 | 02.04.07 | 02.04.07 | 02.02.08 | Tender Termination on date. 22.4.08 | ||
| 32 | Nandgaon Tank | - | - | - | - | - | ||||
| 33 | Bhirata Tank | - | - | - | - | - | ||||
| 34 | Moti Sagar | - | - | - | - | - | ||||
| 31 | 35 | Jeron Tank | M/s Shivdayal | 120.56 | 02.02.06 | - | 02.02.08 | Tender Termination ondate. 22.4.08 | ||
| 36 | Jhiriya Tank | -- | - | - | - | - | ||||
| 37 | Dhubela Tank | - | - | - | - | - | ||||
| 32 | 38 | Gakariya Tank | M/s S.K. Jain | 182.4 | 02.02.07 | - | 02.02.08 | Tender Termination on date. 22.4.08 | ||
| 39 | Bandha Tank | - | - | - | - | - | ||||
| 40 | Phutwari Tank | - | - | - | - | - | ||||
| 41 | Kamodpura Tank |
- | - | - | - | - | ||||
| 42 | Sidhha Sagar Tank | - | - | - | - | - | ||||
| 33 | 43 | Prem Sagar Tank |
M/s Trishul, Jabalpur | 68 | 25.01.07 | - | 24.01.08 | Work completed | ||
| 44 | Nanhi Tehri | - | - | - | - | - | ||||
| 34 | 45 | Bonhari Tank | M/s Azad, U.P. | 39.84 | 09.02.07 | 08.11.07 | Work completed | |||
| GB, Rewa | Rewa | 35 | 46 | Gurma Tank | M/s Vijay Mishra | 1472.01 | 01.06.07 | 01.06.07 | 30.11.08 | - |
| Total | 62162.35 | - | - | - | ||||||
| O & M, Bhopal | Nasrullaganj | 36 | - | SwaRA Bldg. | M/s Mohan lal & Co. | 581.43 | 08.05.07 | 08.05.07 | 07.04.08/ 06.10.08 | - |
| 37 | - | SWaTReC Bldg. | M/s Bansal Construction Works | 287.7 | 08.05.07 | 08.05.07 | 07.04.08/ 06.10.08 | - | ||
| - | - | - | - | - | Grand Total | 63031.48 | - | - | - | - |